A Vision for National Energy

Attarat Power Company (APCO) was conceived to address one of Jordan's most critical challenges: energy dependence. Through a landmark $2.1 billion investment, APCO built and now operates a 470MW(net) power station at Attarat Um Ghudran, fulfilling a national vision for self-sufficiency.

Our Journey & Milestones

Click on any phase node to watch the arrow move along the timeline track and showcase key milestones with visuals.

2006 - 2010
2011 - 2013
2014 - 2017
2021
Commercial Operation
Milestones
2006 - 2010

2006 - 2010

The initial exploration, geological mapping, and concession awards that laid the groundwork for this nation-building asset.

2006

The Journey Began with Mr. Munir Anisla, Founder & Chairman of Near East Investment (NEI).

2008 - 2010

NEI Energia (Enefit) JV signs project Development Agreement with Government of Jordan (GoJ). GoJ awards NEI - Enefit Oil Shale Concession Agreement.

Milestones
2011 - 20132011 - 2013

2011 - 2013

Expansion of operations with global partners, advanced hydrogeological mapping, and pilot shale processing tests.

2011

YTL Power International Bhd joins the project. Commence power plant & mine conceptual engineering.

2011 - 2012

Geological & hydrogeological surveys. 3D modeling & shale testing.

2012

Launch of EPC & Mining Tender. Commence EIA process. Pilot testing of Attarat Oil Shale.

2013

Grid connection legislative framework for solid fuels approved & SDK issues JORC Resource Statement. Commence PPA & EPC Contract negotiations.

Milestones
2014 - 20172014 - 2017

2014 - 2017

Finalizing state agreements, securing massive international banking syndicates, and launching EPC notice to proceed.

2014 - 2015

APCO signed PPA & IA with MEMR & GoJ and EPC contract with GPEC. Commence engineering & financing due diligence. Detailed design for mine & infrastructure. SDK issues JORC Resource Statement.

2016

Signing of financing & Equity Agreements (Yudean joins the project).

2017

Chinese Government approval for Sinosure Guarantee. Financial Close on 16 March 2017; Notice to Proceed issued to EPC.

Milestones
20212021

2021

Heavy plant engineering, structural boiler assembly, and first high-voltage grid synchronization.

2021

Synchronization of Unit 1 materialized with the national grid on 19 May 2021.

Milestones
Commercial Operation

Commercial Operation

Achieved dual commercial operation for both Unit 1 & Unit 2, completing full facility operations and satisfying up to ~17% of Jordan's national electricity demand.

2022

First Unit successfully achieved Commercial Operation (COD) on 25 October 2022.

2023

The second Unit successfully achieved Commercial Operation (COD) on 26 May 2023, completing full facility operations.

2006 - 2010
2006 - 2010

The initial exploration, geological mapping, and concession awards that laid the groundwork for this nation-building asset.

2006
The Journey Began with Mr. Munir Anisla, Founder & Chairman of Near East Investment (NEI).
2008 - 2010
NEI Energia (Enefit) JV signs project Development Agreement with Government of Jordan (GoJ). GoJ awards NEI - Enefit Oil Shale Concession Agreement.
2011 - 20132011 - 2013
2011 - 2013

Expansion of operations with global partners, advanced hydrogeological mapping, and pilot shale processing tests.

2011
YTL Power International Bhd joins the project. Commence power plant & mine conceptual engineering.
2011 - 2012
Geological & hydrogeological surveys. 3D modeling & shale testing.
2012
Launch of EPC & Mining Tender. Commence EIA process. Pilot testing of Attarat Oil Shale.
2013
Grid connection legislative framework for solid fuels approved & SDK issues JORC Resource Statement. Commence PPA & EPC Contract negotiations.
2014 - 20172014 - 2017
2014 - 2017

Finalizing state agreements, securing massive international banking syndicates, and launching EPC notice to proceed.

2014 - 2015
APCO signed PPA & IA with MEMR & GoJ and EPC contract with GPEC. Commence engineering & financing due diligence. Detailed design for mine & infrastructure. SDK issues JORC Resource Statement.
2016
Signing of financing & Equity Agreements (Yudean joins the project).
2017
Chinese Government approval for Sinosure Guarantee. Financial Close on 16 March 2017; Notice to Proceed issued to EPC.
20212021
2021

Heavy plant engineering, structural boiler assembly, and first high-voltage grid synchronization.

2021
Synchronization of Unit 1 materialized with the national grid on 19 May 2021.
Commercial Operation
Commercial Operation

Achieved dual commercial operation for both Unit 1 & Unit 2, completing full facility operations and satisfying up to ~17% of Jordan's national electricity demand.

2022
First Unit successfully achieved Commercial Operation (COD) on 25 October 2022.
2023
The second Unit successfully achieved Commercial Operation (COD) on 26 May 2023, completing full facility operations.

Our Core Values

Our core values guide our decisions, operations, and relationships as we build a sustainable energy future for Jordan.

01

Committed to Excellence
& Integrity

02

Passionate &
Dedicated

03

Accountability

04

Collaborative &
Results-Oriented

05

Continuous Improvement
& Value Creation

Our Companies

APCO
Attarat Power Company

The holding company and lead developer for the Attarat Project with 30-year PPA with NEPCO (Extendable by 10 Years).

AMCO
Attarat Mining Company

Operates Jordan's first commercial oil shale mine at the Attarat Um Ghudran concession (37km²).

Certifications
ISO 9001 Certification
ISO 14001 Certification
ISO 45001 Certification
ISO/IEC 17025 Certification
OMCO
Operations & Maintenance

Operate and maintain day-to-day operations, maintenance, and optimisation of the power station.

Certifications
ISO 9001 Certification
ISO 14001 Certification
ISO 45001 Certification

Senior Management Team

Kiran Kumar
Kiran Kumar
Group Chief Executive Officer
APCO
Zhang Wen
Zhang Wen
Group Chief Financial Officer
APCO
Pang Hanfei
Pang Hanfei
Chief Technical Officer
APCO
Kenneth Laren
Kenneth Laren
Chief Mining Officer
AMCO
Gideon Stans
Gideon Stans
Chief Technical Officer & Station Manager
OMCO

Message from the CEO

Kiran Kumar
Kiran Kumar
Group Chief Executive Officer — APCO

APCO is revolutionizing Jordan's energy landscape with an innovative approach to harnessing the challenging low heat content oil shale – an abundant local resource – for power generation.

Through responsible management and a commitment to environmental stewardship, APCO "powers" Jordan through "rock", marking the first implementation of this transformative energy solution in the region.

Kiran Kumar · Group Chief Executive Officer, APCO